Link between Asana Projects / tasks and Capacity Planning

Hi, is there any link between the estimated time in Asana Projects view and in the Capacity Planning? Let’s say we create a new project, and we fill out an estimated time of 4000 hours for the project (we use the Everhour integration for hour logging). Then, in Capacity planning, we want to add those 4000 hours to the Capacity planning of 3 staff members who will be working on the project. Is that 4000 hours automatically migrated to the Capacity Plan or do we have to re-enter this information manually?

Welcome, @Thijs_Lanckriet,

They’re not connected so you would have to update each separately.

Capacity Planning is a higher-level feature and not as granular as estimated time on tasks.

Another feature, Workload, rolls up estimated time on tasks in a more granular fashion; in this feature, estimated time and Workload are connected.

Thanks,

Larry