Estimated time is one of my favourite fields in Asana, and from what I’ve seen, it’s severely underused.
It’s already in your field library (Asana created it), but it doesn’t get added to projects automatically, so most teams never turn it on. We recommend adding it to every project that’s managing actual work. If you can, do it through a bundle so you’re not adding it project by project. You can also set the base values in a project template.
Here’s why it’s worth it.
If you’re the one doing the work, you can add Estimated time to your My Tasks from the library. Shuffle the field over next to due date and suddenly you can plan your day around what actually fits, not just what’s due. It’s a really simple change, but it makes a huge difference to how you prioritise.
If you’re the one planning the work, this is where it gets really good. Workload defaults to task count, which is better than nothing, but a 10 minute task and a two day task count the same. Switch it to Estimated time and you can actually see who’s loaded up and who’s got room, across a project or portfolio (or your whole instance if you’re on Enterprise and up).
So when Sally calls in sick and she had 6 hours of work booked for today, you can see exactly what needs to move and who has space to take it.
This is also a really powerful view to bring up in stand-ups or weekly planning meetings.
Be careful setting capacity to 40 hours for a 40 hour week. Unless everything someone does lives in Asana, booking every hour they work means they’re behind before Monday morning’s over. Meetings, emails, someone stopping by your desk, all of that is real work, it just usually doesn’t live in a project.
The nice thing is you can set capacity per person, so it can reflect the role. Our default for people who are mostly delivering work is around 6 hours a day. Leaders and managers spend way more time in meetings and on work that doesn’t sit in a structured Asana project, so we’d give them less (how much less depends on the role, what’s in Asana etc).
Stretch goal: add Actual time! It’s also a default library field. Once you’ve got estimated and actual side by side, the gap tells you something you can act on. Do the estimates need adjusting? Does the team need some training? Is the process the real problem?
One thing I’d stress to you, dearest gentle reader, but importantly to your team of Asana users: it’s not about micro-managing or watching people. Everyone wants realistic estimates, because that’s what lets them actually get their work done. We find that when the change management and communication piece is handled well, teams happily adopt both fields and understand they benefit everyone, not just the people at the top.
Are you using Estimated and Actual time? What have you found when you compare them? And if you’ve tried it and it didn’t stick, or you’ve had pushback from your team, I’d genuinely love to hear why.