Why we put Estimated time in (almost) every project

Estimated time is one of my favourite fields in Asana, and from what I’ve seen, it’s severely underused.

It’s already in your field library (Asana created it), but it doesn’t get added to projects automatically, so most teams never turn it on. We recommend adding it to every project that’s managing actual work. If you can, do it through a bundle so you’re not adding it project by project. You can also set the base values in a project template.

Here’s why it’s worth it.

If you’re the one doing the work, you can add Estimated time to your My Tasks from the library. Shuffle the field over next to due date and suddenly you can plan your day around what actually fits, not just what’s due. It’s a really simple change, but it makes a huge difference to how you prioritise.

If you’re the one planning the work, this is where it gets really good. Workload defaults to task count, which is better than nothing, but a 10 minute task and a two day task count the same. Switch it to Estimated time and you can actually see who’s loaded up and who’s got room, across a project or portfolio (or your whole instance if you’re on Enterprise and up).

So when Sally calls in sick and she had 6 hours of work booked for today, you can see exactly what needs to move and who has space to take it.

This is also a really powerful view to bring up in stand-ups or weekly planning meetings.

Be careful setting capacity to 40 hours for a 40 hour week. Unless everything someone does lives in Asana, booking every hour they work means they’re behind before Monday morning’s over. Meetings, emails, someone stopping by your desk, all of that is real work, it just usually doesn’t live in a project.

The nice thing is you can set capacity per person, so it can reflect the role. Our default for people who are mostly delivering work is around 6 hours a day. Leaders and managers spend way more time in meetings and on work that doesn’t sit in a structured Asana project, so we’d give them less (how much less depends on the role, what’s in Asana etc).

Stretch goal: add Actual time! It’s also a default library field. Once you’ve got estimated and actual side by side, the gap tells you something you can act on. Do the estimates need adjusting? Does the team need some training? Is the process the real problem?

One thing I’d stress to you, dearest gentle reader, but importantly to your team of Asana users: it’s not about micro-managing or watching people. Everyone wants realistic estimates, because that’s what lets them actually get their work done. We find that when the change management and communication piece is handled well, teams happily adopt both fields and understand they benefit everyone, not just the people at the top.

Are you using Estimated and Actual time? What have you found when you compare them? And if you’ve tried it and it didn’t stick, or you’ve had pushback from your team, I’d genuinely love to hear why.

9 Likes

Adding Estimated time to My Tasks now :+1: Agreed that Estimated time is very underused (and I’m guilty of it too)!

I agree it’s useful and this post was a good reminder of why. That said, it’s hard to justify spending the time to fill in the estimated time, particularly for smaller tasks. If it takes 10 minutes a day to fill in the estimated time, I could have done 10 minutes worth of actual work! It’s also very easy to fall behind on not filling it in for every task, which quickly makes the workload view less reliable.

Any tips on how you’ve managing keeping up with adding this field quickly and easily? Do you restrict it to tasks that take 1 hour or more?

1 Like

That is a really good point, and it’s a common challenge we’ve come across, especially for adhoc work where the project template isn’t doing the heavy lifting of prepopulating it for you.

It depends on the use case I suppose, and how much of your work is ‘structured’ (project template generated or recurring tasks etc) vs adhoc.

You’re right though, on those adhoc tasks, I wouldn’t be bothering to populate the estimated time unless it was a meaningful block - even 30 minutes might be meaningful, but that number could be different for everyone depending on how the scheduling works and ultimately the risk/impact of missing a deadline.
As a general rule, my advice is to be trying to plan your capacity hours in workload view around that controllable work, and allowing the remaining amount to cover the adhoc work.

This also means you don’t end up having to create a task for every single meeting you attend. It can easily become admin overhead if you let it, but taking an approach that suits 80% of the time is generally enough for someone to manage that workload view.

So, how that looks in our own team:
I am the Practice Lead, so I am not on full time project work - I train my team, assist with the sales opporitunities, have leadership meetings etc. So from a workload perspective, the controllable part for me is that I only want to have about 8hrs of planned project work on my plate a week to be able to achieve all the other things I need to do.

My team are primarily working on our client implementations, so we aim for their workload capacity to be at about 30 hrs per week, which still gives them time for our team meetings, emails, getting a coffee and some tasks taking longer than expected, but it also gives us a solid view of when work can be done. On that too, some weeks they are over capacity slightly because of a deliverable being due or similar, but if their capacity goes red and I expand the view to see their tasks and I know it’s over by 30 mins on 2 days, I also know it’s fine and manageable.

I hope that makes sense and helps you consider how you might make it work! I’d love to hear what you think.