Introducing project "Duration" and "Time Remaining" fields in Portfolio List View

@Michelle_Paulino, Yes, in the Starter/Legacy Premium plan and above you can add a Gantt view to any project which includes a duration column.

Thanks,

Larry

1 Like

Great news!
However, will these fields be available on in Project view soon? Would be great for those who are using the time tracking feature.

Hi @Paige_Thai , if you are on the Advanced tier (legacy Business plan) you can actually create a formula field that will show you a task’s duration (not an input field).

Have a look at point 1 in this post:

I have not managed yet to use the duration column in the portfolio view in the portfolio dashboard. One of our KPI is the duration of a project. I would love to report on this number. Also, is there a possibility to show the duration in days instead of weeks?

Hi @Stephanie_Teixeira , welcome to the forum :wave:

You can create your own duration formula field, formatted in days as per point no.2 in this post: