How to specify working days for capacity

Hi, in Portfolio / Workload I can specify that someone works 20 hours per week but how can I specify the days of the week the person is working on? I don’t want to have these 20 hours divided over 5 working days.

Hi @Frank_Sonck, thanks for reaching out! Tasks taking place at the weekend are split automatically over weekdays. I’m afraid it is not possible to manually adjust this distribution. When you have a task with multiple days, Effort will be split evenly over weekdays (skipping weekends). For example, a 10 hour task over 2 days will be 5 hours each day. If the task goes Friday to Monday, it will be 5 hours on Friday, 5 hours on Monday.”

I hope this helps! :slight_smile: