We are a nonprofit that serves families and I am trying to set up quarterly check in’s. Currently new referrals import into our project as tasks and we have a rule set up that once we change the tasks section to “Intakes” it creates the list of subtasks.

One of those subtasks is quarterly check-in’s. How can I set it so that the subtasks auto schedule 90 days apart from each other? I made each task dependent on the previous one and was hoping that I could set the due date to 90 days after the prior task was completed.

Welcome to the forum, @Megan_Goodbar! You should be able to use task recurrence for this. In the due date, click the little circular arrow to open up the recurrence menu: