Hi All,
Quick question… Is there a way to change a date on a single tasks, and have that cascade to all other tasks.
This is how the old MS Project software us to work.
Hi All,
Quick question… Is there a way to change a date on a single tasks, and have that cascade to all other tasks.
This is how the old MS Project software us to work.
@Jack_Vitulli: “Auto-shifting dates for dependent tasks” under Task Dependencies might help with this situation.
Hi @Jack_Vitulli Welcome to the Forum!
You can change the due date in bulk by multi-selecting the tasks and setting a new due date for those selected tasks.
I hope this helps! Please let me know if you have any follow-up question!
Happy friday!
Thanks Benjamin…
It seems straight forward enough, but I suspect that it only works for Premium accounts?
All my tasks are dependant, but when I change the date on the top most one, nothing happens to the subsequent task dates.
Correct - dependency auto-shifting is not supported in free accounts.