Can I ripple my timeline forward in gantt chart mode?

I have a project with loads of dependencies. The dates all start with a production (filming) date - but when I move the filming date forward in time, the associated tasks do not move forward.

Is there a way to move all dependent tasks forward relative to the one key task (and date) that have moved?

Thanks for any help!!

Hi,

If you go to the three dot menu of the Timeline there is a dependency conflict avoidance you can toggle on that would do exactly what you are describing. It should be enabled by default. Can you check and get back to us here?

Thanks, hope that helps.

1 Like

Thank-you, that worked!