Auto Add Milestones to New Project

I am looking to automatically add any tasks that are converted to a milestone to another project. I looked in the custom rules options and not seeing the ability to do this…am I missing something? Or any suggestions/work-arounds?

Thanks in advance!

Welcome, @Maddy_Lundquist,

A workaround would be to add an “Action” (or similar) single-select custom field with a single value “Convert to milestone” (more later when/if you have more actions).

Add a rule:

  • When Action changed to Convert to milestone
  • Do this:

    and add to another project
    and reset the Action field

Thanks,

Larry

2 Likes

Hi @Maddy_Lundquist,

FYI another option is a rule in our Flowsana integration, which lets you do this:

2 Likes

Great workaround - thank you!

1 Like