@Iren_Vilaniso ,
I think it’s critical in answering a question about cross-project dependencies to raise this serious Asana limitation–a real “gotcha” for many:
Hi all,
TL;DR - Changes to due dates on tasks with dependencies across different projects should update due dates of dependent tasks in all projects (or pop out a modal asking user to approve date changes in other projects).
My use case: I have projects with many components. Sometimes, individual components will spawn new projects that have a few tasks/milestones multi-homed back to the original project.
My ask: I would like those multi-homed projects to have dependencies in both the originat…
Thanks,
Larry