Templates & due dates: having both "days before" and "days after" within the same project

You can use a formula field :slight_smile:

Hi there, I’m wondering if there’s a way to automate or set rules for due dates in subtasks within Templates to work backward?

For instance, if I create a task from a template and manually set a due date for the task, say June 30th, is there a way for certain subtasks to automatically get due dates, such as 2 weeks before the task’s due date?

I’m looking for a solution that doesn’t require integration with external sources, ideally something that can be done within Asana alone. Thanks for your help!

Here’s the process for clarity:

  1. Create a New Task using a Template
  2. Set manually a Due Date for the Task (e.g., June 30th)
  3. Subtasks Automatically Receive Due Dates (e.g., if set 2 weeks before the task due date, it would be June 17th)

Appreciate any help you can give. Thank you!

Hi @Gabriel_Maureen_Cri1, thanks for reaching out! It’s currently not possible to add relative dates before the task is due in task templates. I’ve gone ahead and merge your post with Templates & due dates: having both "days before" and "days after" within the same project to consolidate feedback. We will let you know if this is something we plan to implement in the future!

Hi Emily, appreciate your help on this. May I ask if the image that Mr. Bastien sent last April 2022 is not the version/feature available now? I can’t see the option to select ā€œAfter/Before project start dateā€ on my end.

image
f90e650944edda1ef26c6648b3be1349855ba394_2_595x500
Here's what I can see on my end

@Emily_Roman

It’s there; you need to click that little pencil icon to the right of ā€œAfter project start dateā€.

Appreciate your assistance, Phil! The 1st and 2nd photo comes from the other writer/user above. The third photo is what shows from my end. For some reason, there’s no pencil icon or option to select the Due Date rule. Is this something that is not available anymore with the updated version of Asana, or maybe because of my subscription or User permission?

Will appreciate any help given.

@Gabriel_Maureen_Cri1,

Apologies, I got confused because the screenshots were not identified as to their source.

Also I should have read further up the thread - I see now you’re asking about Task templates which are completely different from the topic of this thread which is Project templates. The screenshot and the pencil icon applies to Project templates.

As Emily said, what you’re asking for can’t be done in native Asana for a Task template.

Thank you so much for the clarification on this. Is there a way that this can be done with the help of integration or other methods? Do you have a recommendation in mind? Thanks!

You can do it with the Add subtasks rule action in our Flowsana integration. That’s not exactly the same as a task template - you would need to trigger the subtasks to be added based on some rule trigger as opposed to a user manually adding the subtasks by selecting a task template - but it’s one option.

I am trying to do the same thing would love to see your template if you care to share.

I’m pleased to inform you this is now a thing. :slight_smile:

1 Like

Amazing news! I still need the due dates in the before and after format when it comes to task templates. We use one asana project per client, and have multiple projects for the same clients that we host in the same project. We use task templates to generate a new series of tasks for a project, but these are relative due dates and are calculated based on when the task is created and not based on a set due date.