Request Changes approval makes a task behave as if completed.

Briefly describe (1-2 sentences) the Bug you’re experiencing:
When a user marks an approval task as ‘rejected’ or ‘request changes’, the task behaves as if it is completed and disappears from a users ‘my tasks’ area.

This means when we reassign a task because changes are needed, the user can’t see the task that has been assigned to them, or, a person can’t keep track of tasks that have not been approved.

Steps to reproduce:
Mark a task as an approval task.
Select ‘request changes’ or ‘rejected’
The task disappears from the assignees ‘my task’ list

Browser version:
Chrome and Safari

2 posts were merged into an existing topic: Approvals - Request change should keep the task incomplete