QQ: How can I reorder milestones?

I am building out my Project Overview. It allows me to start listing milestones. Somehow, I inserted some in the middle that should be at the end and vice verse.

I can’t figure out how to move them around to reorder them.

Any help?

T.I.A.
-dan

@anon23352771,

In Project Overview, Milestones appear in order by

  1. First, those without a Due date in the order of appearance in the unsorted project List view from top to bottom, and
  2. Second, those with a Due date, in ascending Due date order

You can’t change those rules, but you can affect a Milestone’s position in the list by its having a Due date or not, and if no Due date, by shifting it up/down in the unsorted project List view.

Hope that helps,

Larry