Project Template with task due dates based on start AND due date

The use case I need is a template of 20-30 tasks that are created when we sign a contract for an event. Some of those tasks need to be due x days AFTER contract signing and some of them need to be due x days BEFORE the event date. The overall timeline from contract to event is variable so it needs to be based on both. I’ve only been able to figure out how to do one or the other, can anyone help?

@Micaela_Wall,

This isn’t something you can do. This requires 2 seperate templates, one with all of the tasks dependent on the start date & the other based on on the project due date

From there, if you need to see everything together, you can merge the projects together. The easiset way to do this would be to use bulk-edit to multi-home.

Best of luck,
Christine

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.