Hi,
The Workload view is great to analyse the past and look at the upcoming workload of users. Capacity Plan is great to simulate allocations of projects in 3-6 months.
But then what happens in between? How do you deal with that “gap” between workload and capacity plan? Any advice?
2 Likes
This is amazing, and I’m interested in other users’ use cases.
One thing I can think of:
Create an “Allocations” project
Create a simple project just for planning the next 4–8 weeks
Add placeholder tasks like:
Task: John – Project A – 20h
Task: John – Project B – 20h
These tasks don’t represent actual work yet, but they represent planned effort
As plans become more concrete:
Move or multi-home these tasks into the real projects
This allows them to show up properly in Workload (You can see overload before work even starts)
You’re converting capacity planning into task-based “effort signals” so Workload can visualize it.
Yes so basically do what we were doing before the Capacity Plan even existed. But it does notify people 
1 Like