I want to be able to run a report on:
All projects due in 1 week
All projects due in 3 days
All projects past deadline
But when I run reports with Due Date within the next 1 week I also get overdue reports (some going back years. Now I realize this may partly be us not cleaning up our projects - but I donât want to see overdue - I want to just see whatâs coming up.) I realize I can filter it further by saying âcreated withinâ but that kind of filtering can be a little bit tricky - what if you have a report thatâs going on for months and falls outside that created by date, and you miss it?
And I canât seem to find a way to run just projects that are OVERDUE.
Am I doing something wrong? Or is this a bug?
Thanks!
To get Todayâs task â âtask with due date within the last 0 daysâ
To get Todayâs and overdue tasks â âtask with due date within the next 0 daysâ
To get overdue tasks â âtask with a due date between 01/01/00 and todayâs dateâ
Does that help?
2 Likes
This is not helpful for an advanced search where you want to create a report for tasks due within the next 3 days for example. When I create this it is still showing overdue tasks.
@Bastien_Siebman Just learning how everything works here. I just want to make sure you see my reply from two days ago. Many thanks!
Indeed. Then you can use this, but youâll have to change values all the time :s
@Bastien_Siebman thatâs too bad. Hopefully this will change in the future but I can keep updating the dates in the report for now. Thanks for flagging and thanks for the work around!
Hi everyone!
This is just a quick update to let you know our team is rolling out an update to solve this issue. With this update the results in your reports will truly be only tasks with due dates in the future.
If you still see overdue tasks or tasks with different dates when searching for tasks within a specific timeframe or if you have any questions please let me know and Iâll be happy to assist you further!
1 Like