Indicate custom non-working days in Timeline, Gantt (and Calendar) views

I’m chuffed that this has been released exactly as I had imagined:

However, in the Timeline and Gantt views, the weekends are still visually displayed as defined by the user’s Settings>Display settings which are still a bit limited to just ‘conventional’ 2-day weekends - this is a bit unfortunate as a user cannot visually see the custom non-working days in these incredibly useful project views.

Requesting to add a darker shade of grey to indicate the custom non-working days, apart from just the 2-day weekends

In the below example, Friday is set as the only working day. The Duration column is correct; the task starts on Thursday, it skips Friday and ends on Saturday (which is a working day). However, the grey shade is applied to Sat & Sun, not on just Friday, in this example.

I’m personally not a fan of the Calendar view, but I will throw it into here as I’m sure it would be beneficial for those that use it.