OK Kalen here is my attempt to facilitate your weekly reporting requirements.
- At the top of each project create a section that says Weekly Reporting Status
- Create A reoccurring task for every Friday titled Weekly Status Report or if you want more detail include Team name and Client or whatever you want. It will still have the custom field Weekly Status in it.
- Adopt the Red-Yellow-Green status by creating a custom dropdown field called Weekly Status and hide in the column. Custom Fields are in Premium but 5 members start at about $250 per year. Don’t know if you are a Premium member or not.
- The manager in charge of the project would be required to use the drop down to mark the status of the project.
- In the description box the manager writes a couple sentence description and:
- If there are tasks within the projects that are stucks he includes them as a hyperlink in the description box.
- Write an Advance report for incomplete task that the custom field Weekly Status is marked Red, ( The first priority for your company to know about and any of the tasks that are hyperlinked).
- Sort on Project
- Save as a Report Favorite and change name to whatever makes sense.
- Do the same thing for Yellows and Greens if necessary. Some companies prefer not to spend time on projects marked as Green as they are on track.
- Because the Team is not shown, you can see I am using an abbreviation at the start of each project name to identify the team. There have been requests to add the Team to this type of search.
I actually think this is as effective as the Dashboard feature because it is faster to scroll through and includes reference to tasks that are your “stucks” by there hyperlink reference.
I am attaching the Advanced Search for an example.
So there is one man’s thought but I am sure there are others. This is consistent with the book I referenced.