Workload - missing purple area

Hello, how are you? Can you help me, I can’t see in the workload of the portfoli. It shows me the resources but not the workload (the purple area from the team). They have assigned tasks. I’m sure I’m missing something but I don’t know. I appreciate your support. Thank so much

Hi,

I am great thank you. If nothing shows up it could be because the tasks don’t have dates. Or, if you chose an effort (a custom field) then maybe those tasks don’t have a value in them?

Let us know.

1 Like

Hello,

Thank you very much for your reply. It was that, I had chosen a custom dedication field and did not had a value in them.

I apreciate very much for your reply.
Regards, Blanca

1 Like