Our marketing team has several custom fields that are tracked at the top-level task for each deliverable, like the type of deliverable, its client, its project manager, etc.. The subtasks for each step of the creative production rarely only go beyond one level, so it’s been nice to have the inherited fields a click away for each subtask.
Our marketing PMO developed a recommended display for the marketing team’s “My Tasks” tab, including prescribed filters, sorts, and select custom fields to display. Unfortunately, the custom fields in “My Tasks” are typically blank, since they are displaying the fields for the subtask, rather than the inherited fields from the parent task.
Is there a way to natively display an inherited field of a subtask in “My Tasks”? We’ve experimented with some integrations, but are seeking a native solution.
I want to follow this thread because my team has been having similar struggles with subtasks in their My Tasks screens.
One option we tried (but it seemed to be the reason our project templates started crashing) was to have subtasks “multihome” into the top level of the same project, so that when using My Tasks, one could sort/group tasks by Project, as an example. If the subtask was not also displayed in the top level of the project, grouping by Project would not work. When we set this up as an automation, our project template crashed (s/o to Connie in CS and the engineers who helped us with a fix!). Despite having a workaround and a fix, i would not recommend this as it was convoluting a lot of the task ownership.
To actually answer your question @stephenatdrexel I think if a Custom Field is in your organization’s library, everyone should be able to add it to their My Tasks view and it should update within that view as well as the project views. I could be wrong though!
Hi @stephenatdrexel, currently, there isn’t a native way to display inherited parent custom field values for subtasks in My Tasks. My Tasks only displays custom fields that are directly assigned to the task or subtask.
Here are a few possible workarounds:
- Add subtasks to the same project as the parent task: You can manually add them or create a project rule to automatically add new subtasks. However, the custom field values will still need to be entered on each subtask, as they won’t automatically sync with the parent.
- Keep important steps as top-level tasks: This allows you to filter and sort by custom fields such as client or deliverable type in My Tasks.
- Use a saved project view or dashboard: This can help report on parent-level custom fields across your team’s work.
I hope this helps!