timeline adjustment

Looking for a way to “select all” when making timeline adjustments. For example, if the entire project needs to shift by one week, how can ALL the timeline tasks be adjusted without having to go in and change each task one by one?

Welcome to the Forum @cynthia_favret and thank you for reaching out!

That is a great question! I can confirm you can multi-select tasks in timeline to shift them all at once. Please have a look at Larry’s indication here to learn how.

You can find more information on Timeline in the following guide article.

I hope it helps Cynthia! Please let me know if you have any follow-up question!