Time dependencies

When dealing with production/development projects a typical dependency is “beginning-beginning”.

For example: two step production
Task A: production step 1 takes 4 weeks for 400 parts
Task B: production step 2 can start after the first 100 parts (1 week after Task A started)
The dependency would be “beginning-beginning +1week”

Is it possible to realize that?