How to show, the task count in the Dashboad, for tasks that was completed within 24 hours ?
I have meetings on Mondays, and want to show how many tasks were completed for the previous week… (7 days) were creation date & completed date was within 24 hours…
As far as I can see, this is not possible
A workaround:
-
Create a formula field “Throughput time” and have it calculate
created_on - completed_on
:
-
Save a view with completed tasks created last week:
-
Sort by Througput time
-
Create another field (single select) “Completed within 24h” with values “yes” and “no”
-
Before your meeting, multi select all the tasks that are completed within 24h and mark them with “yes”, and for the tasks that aren’t completed within 24h mark them “no”
This should only take a couple of minutes each week before the meeting, and should provide you with the fields needed to create that dashboard.
As this is currently the closest thing I can think of to solve your request I’m marking this as a solution.
If you’d like me to move it to Product Feedback to suggest to Asana they implement your initial suggestion let me know.