Strikethrough completed tasks (instead of disappearing)?

I’m new to Asana. In some cases, after I complete a task, I want to see it in the list with a strikethrough or “completed” designation. Is this possible? Right now when I mark a task completed, it disappears. Thank you.

1 Like

@Seth_Stark yes, that’s possible. Near the top of the project, click where it says Incomplete tasks and Select All Tasks. You should now see completed tasks checked off in your project.

image

3 Likes

Perfect! Thank you.

1 Like