# Static Start and End Dates Not Effected by Dependency Date Shifting

**URL:** <https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506>\
**Category:** Ask the Community\
**Tags:** dependencies, agentic-work-management\
**Created:** [May 11, 2026, 3:12pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506 "2026-05-11T15:12:44Z")\
**Posts on this page:** 8\
**Page:** 1

<div class="post-metadata">

**Author:** ![Carly\_Rowaan](https://luna1.co/8d76cd.png) [@Carly\_Rowaan](https://forum.asana.com/u/Carly_Rowaan)\
**Post date:** [May 11, 2026, 3:12pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/1 "2026-05-11T15:12:44Z")

</div>

It would be incredibly helpful if there was an option to have a project start and end date remain unchanged by maintain buffer or consume buffer on dependent tasks.

The projects I work through and manage have very firm start and end dates, however tasks within the date range may change based on individual team member availability and workflows.

Is there a way that if a dependent task date needs to change, by either maintaining buffer or consuming buffer, the start and end date of a project still remains the same? I don’t mind if some tasks over lap, but my start and end dates need to be static.

Its not helpful to have upstream of downstream tasks push out my start or end dates in these instances where there are firm deadlines.

---

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [May 11, 2026, 7:16pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/2 "2026-05-11T19:16:10Z")

</div>

@Carly_Rowaan,

I believe Asana already works this way.

The project start/due dates are here in project settings:

 ![image](https://us1.discourse-cdn.com/asana/original/4X/8/6/4/86489fcac2f0ba08c52a0e6f11e12668831c28bb.png)

They’re set manually and not affected by tasks’ start and due dates.

Thanks,

Larry

---

<div class="post-metadata">

**Author:** ![Carly\_Rowaan](https://luna1.co/8d76cd.png) [@Carly\_Rowaan](https://forum.asana.com/u/Carly_Rowaan)\
**Post date:** [May 11, 2026, 8:29pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/3 "2026-05-11T20:29:41Z")

</div>

My experience thus far is that when I have dependent tasks set to either consume buffer, or maintain buffer, it will change my start/due dates for the project. I’m hoping for an update to allow the option make the start/end dates static so that only the tasks in between can change dates.

---

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [May 11, 2026, 9:01pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/4 "2026-05-11T21:01:52Z")

</div>

Maybe you’re talking about dates of tasks (one task representing project start and one task representing project end) whereas I was showing Asana’s built-in dates of projects.

If you’re using two tasks as above, you could remove their dependencies.

---

<div class="post-metadata">

**Author:** ![Carly\_Rowaan](https://luna1.co/8d76cd.png) [@Carly\_Rowaan](https://forum.asana.com/u/Carly_Rowaan)\
**Post date:** [May 11, 2026, 9:16pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/5 "2026-05-11T21:16:50Z")

</div>

Yes, sorry that’s what I was talking about. There are project milestone tasks that serve as a firm deadline within the project, that would benefit me as being static.

---

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [May 11, 2026, 10:48pm UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/6 "2026-05-11T22:48:57Z")

</div>

Ok, remove their dependencies for each of these tasks and they won’t participate in the date shifts but all the other tasks will continue to participate.

Thanks,

Larry

---

<div class="post-metadata">

**Author:** ![Motor](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/motor/32/34301_2.png) [@Motor](https://forum.asana.com/u/Motor)\
**Post date:** [June 5, 2026, 11:08am UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/7 "2026-06-05T11:08:25Z")

</div>

Issue not solved.

For proper Project Management, there must be a way to anchor Critical Path tasks and be notfied visually if theres risk to critical path anywhere on the timeline.

If Asana is serious about being a project coordination tool or PM tool, this is a very important feature that’s required. Taking the Critical Path items out of the dependency chain doesn’t make any sense to me.

---

<div class="post-metadata">

**Author:** ![system](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/system/32/276370_2.png) [@system](https://forum.asana.com/u/system)\
**Post date:** [July 5, 2026, 11:08am UTC](https://forum.asana.com/t/static-start-and-end-dates-not-effected-by-dependency-date-shifting/1140506/8 "2026-07-05T11:08:34Z")

</div>

Closed on July 5, 2026, 11:08am UTC

This topic was automatically closed 30 days after the last reply. New replies are no longer allowed.