Reporting on tasks without estimated time

Is there any option to report on tasks that have no estimated time set?
Id like to track who does not use this function.

@Aleksandra_Czepierga - yes, you can use Advanced Search and filter by tasks that do NOT have any value in the Estimated Time field.

It’ll need to look like this (see the added custom field filter for Estimated Time at the bottom)

  1. Click in the search bar and select Advanced Search (probably a toggle to the right side, but might be an option at the bottom of the search dropdown).
  2. Click on “Add filter” at the bottom left
  3. Add custom field
  4. Select Estimated Time
  5. Select “With no value”

That should do the trick. Then you can click at the top right and select to Sort By Assignee to see who has several tasks without an entry in Estimated Time.

You could also filter by tasks with a due date, “Through the next” X number of days so that you are only seeing the results for PLANNED tasks that have due dates.

If you like and want to repeatedly re-use this search, click on the Star at the top left to save the search.