Hi! I’d like to create a report that includes all incomplete tasks assigned to members of the teams I manage, as well as My Tasks, many of which are private to me and not assigned to a project. I don’t see a way to pull My Tasks into a report with other assignees and projects. Is there a way to do this? Thanks!

Hi Lisa,

If you create an advanced report it will pull up all of your incomplete tasks, even if they are in a locked project from your team. The reports are segmented from any other user so no one will be able to access your advanced reports. If you set up an advanced report something like what I have below you should be able to pull all of the tasks up and then you can filter by assignee.

image

I hope that helps,

Katie

2 Likes

Haha, I guess I should have been able to figure that out. Exactly what I needed. Thank you, Katie!