Hello! How do fellow Asana users handle the following scenario?
We have a project that is being worked on and contains multiple steps, say 50 to 100, call it project A. We want Project A to be visible as an item on another board, Project B, but not necessarily the individual tasks and subtasks of Project A. What we have done, is created a task in Project B which is essentially just a link to Project A with a note that you can find the details of Project A by following the link. It works okay. But I’m thinking there could be better ways to maintain this visibility into Project A without multi homing all the steps to Project B as that’s way to much detail for those interested in Project B.
Hi,
I believe your approach is the right one. You can also decide to multi-home milestones or only specific tasks from A to B.
Hope that helps.