Project tag tasks as a bulk to another folder vs 1 by 1 project tag?

Hi team,

Is there a way to bulk project tag tasks from a folder to another vs doing it task by task?

Hi,

What do you mean by “project tag tasks”? Are you referring to tags on tasks?

Is there a way to select all of the tasks items as a bulk so I can tag them to another same place folder? (image example)

Yes! In any List View, you can left-click on the first Task of interest, then Shift+left-click on the last, and all those Tasks will be selected. Edit one of them as to Tag (or Project or Custom Field or Due Date or …) and you’ll find that all of them are changed at once.

As far as I know, you can only do this 1 visible screenful at a time.

1 Like

You can multi-select up to 50 tasks at a time.

1 Like