Is it possible to ‘pre-assign’ a task to a team member, but not have them notified?
When planning and scoping projects it is useful to assign tasks to team members, but I don’t want them to notified and hence be distracted with speculative tasks. These tend to clog up their inbox and task list.
Hi @Gordon_Dobie. As soon as you assign a task to a team member, they will be notified. One option (if you have a business tier plan), is you can set-up a custom rule with the Trigger/Action: Task is no longer waiting → assign task (you can specify owner). And you would make the speculative task dependent on another prior task.
1 Like
Welcome to the Forum @Gordon_Dobie and thank you for reaching out!
Adding to @Bernie_Orelup’s great suggestion, in case you are not in a paid plan, you might find the following workaround very helpful.
We also have a thread in the #productfeedback category regarding this topic. In case you haven’t yet, I would suggest you to upvote it: Pre-assigning task to people
I hope this helps Gordon! Have a great week!