Pipelines - add new tasks into a pipeline?

Hi,
In a simplified view, silicon design goes through the following stages: “specification”, “design”, “review”, “layout”.
I have ~40 blocks which need to be designed. I also want to know when this project is going to finish.
I’ve read the documentation and concluded that you can’t add new tasks to a pipeline because Asana doesn’t let you copy “Sections”.

  • If I have one task which progresses through different “status” as progress is made, I won’t see a project end date.
  • subtasks don’t appear on the timeline so are of no use to me as I can’t manage resources.

Please can you add the ability to copy sections?

2 posts were merged into an existing topic: Ability to copy sections including all tasks in that section