Not sure when the process changed, but we have been using project templates inside portfolios for years. After creation, the project was always added to the top of the list.
Recently, we noticed that the behavior has changed, and new projects are now sent to the bottom, below all of our completed projects in the portfolio. Support confirmed that this change was intentional, and the only workaround they provided was to drag the new projects all the way back to the top.
My question is, has anyone else noticed or had a problem with this workflow? If so, do you have a better workaround?
Two things you could try. Sort the portfolio list by a column like start date instead of keeping manual order, then new projects don’t sink to the bottom.
Or move finished projects into a separate archive portfolio. That way the main one only holds active work and there’s nothing to drag past.
Thanks for your thoughts. The issue is inside the portfolio; we like to manually sort based on the current status. We don’t need projects on hold to be at the top, even if they were created after a project that is in progress.
Secondly, we already have enough portfolios to keep track of; adding additional ones for archives does not make sense for our team (especially when we had a functioning workflow for years).