"My Tasks" in weekly view is not showing all tasks

Weekly view is showing a total of 23 tasks only at a time, it seems I can swap tasks in, but for some reason it removes another task out of the view. I have no filters on, I have cleared cache, uninstalled and re installed, restarted. Nothing has worked. My tasks are still there in the monthly view, but not in weekly???

This is disrupting my day as I can’t order my tasks (for some reason this is not a feature on the monthly view??) and it is difficult to go through my tasks and actually know what I need to do next up

Hello @Yasmin -I am very sorry to hear that this has been disrupting your workflow. This appears to be intended behavior. I did some testing and I was only able to have a maximum of 20 tasks appear for a specific date on the calendar view, set to week. I will note down your feedback for our team.

@Yasmin, In case you weren’t already aware, a workaround would be to use My Tasks List view, adding a tab there that’s grouped by Due date:

You’ll see a display like this, with no limitations on the number of tasks in each grouping:

Thanks,

Larry

1 Like

This wasn’t the same behaviour before this update.
I use the weekly view the same way as Yasmin, ordering the daily task in the planned sequence of completion. when there are more than 20 task, a vertical scroll bar would appear so that we can see a list of items to be completed. I would like to request that this 20 task limit be reversed and to bring back the vertical scroll bar.

1 Like

Wow this is something that is intentional?! This is awful! There’s no other view that I can see the colour of my tasks (which I organise based on project and department). I’d really not like a workaround! I’d like to be able to see my tasks in one place as before without having to adjust filters each time.

Is there at least a way to install a historic update? this is severely impacting my way of working and productivity, and I’m having to try to get used to an entirely new way of working because of this.

Monthly view gives the colours but you aren’t able to organise the order they show in?!

Is the limit of 20 tasks per day in the weekly view surmountable with a different pay plan or is it present in all plans?

I am part of my companies organisation which is part of a paid plan

Hello @Yasmin - It appears that the limit of 20 tasks on the calendar view was a bug and it has been resolved!

3 Likes

Indeed! Thank god! It has been fixed for me as well.

2 Likes

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.