Multiple dependencies between the same 2 tasks

Currently we can define only 1 dependency between 2 tasks. Why?

I want a task to happen in the middle of another one, Hence I need SS and FF dependencies between the same 2 tasks.

Typically the first task will have long duration, and the second one will be planned based on dependencies with other tasks (but still within the first task!).

Sounds like something that indeed cannot be done with Asana. It also sounds like a very specific use case in project management that might be the reason why this is not covered. The “why” is simply that it is not useful to 99% of users, might be the reason why you didn’t make the cut.

Well it will be the case for all support tasks: any support task shall happen within the supported task. So it does not look very specific to me, especially if you have a lot of resources to manage.

I am also missing some other stuff regarding the API, which are not planned to be implemented. So I guess I belong to the 1% users who may leave Asana.

Could you elaborate to the why behind the needing for these dependencies?

This is helpful in suggesting workarounds.

Also, don’t forget to vote for your own feedback. :wink:

@Erik_Labadie, If you’re open to a workaround until/if Asana offers the feature you request, did you already rule out the use of subtasks as a way to accomplish what you’re seeking right now?

Thanks,

Larry

sub-tasks are not the way I want to go because:

  1. It is anyway possible to define a sub-task outside the time window of its parent
  2. Parent and child tasks are then grouped in a way that is not my primary focus (see example below)
  3. In my own internal analysis & planning tools I dont want to distinguish between task and sub-task, I just want to consider the dependencies between tasks (therefore I need to be able to define them…)

Here is an example.

I have lots of tasks for my SW team, which are driven by the lifecycle of the SW. But I want SW team to also support the system requirement team by reviewing parts of the system requirements. The requirement tasks are driven by the lifecycle of the system activities. I dont want to first mix SW and system tasks (this would also make resource management even more difficult), I just need some dependencies between system and SW…

1 Like