# Moving Tasks Between Projects

**URL:** <https://forum.asana.com/t/moving-tasks-between-projects/84937>\
**Category:** Ask the Community\
**Created:** [29 May 2020 19:20 UTC](https://forum.asana.com/t/moving-tasks-between-projects/84937 "2020-05-29T19:20:48Z")\
**Posts on this page:** 3\
**Page:** 1

<div class="post-metadata">

**Author:** ![anon64816647](https://luna1.co/8d76cd.png) [@anon64816647](https://forum.asana.com/u/anon64816647)\
**Post date:** [29 May 2020 19:20 UTC](https://forum.asana.com/t/moving-tasks-between-projects/84937/1 "2020-05-29T19:20:48Z")

</div>

On Project A’s board I have added a few different columns such as type of task, priority, time estimated, ect. I use the columns when I input a task, but then when I move the task from Project A to Project B all of these columns are lost in the transfer. Is there a way to move a task from Project A to Project B and still maintain the customized columns I added?

---

<div class="post-metadata">

**Author:** ![Phil\_Seeman](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/phil_seeman/32/81525_2.png) [@Phil\_Seeman](https://forum.asana.com/u/Phil_Seeman)\
**Post date:** [29 May 2020 19:38 UTC](https://forum.asana.com/t/moving-tasks-between-projects/84937/2 "2020-05-29T19:38:26Z")

</div>

There are two type of custom fields: project-specific and global, where by global I mean custom fields that live in your organization’s custom fields library.

If the values are not copying over, that means it’s a project-specific custom field. To remedy that, edit the field and check the box “Add to [your org name]'s field library”. That will turn it into a global field. Then go to the second project, delete any project-specific field you may have added there with the same name, then add the newly-global field by using the “Choose from library” tab.

Let me know if any of the above doesn’t make sense or if you have any further questions!

---

<div class="post-metadata">

**Author:** ![system](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/system/32/276370_2.png) [@system](https://forum.asana.com/u/system)\
**Post date:** [27 April 2022 14:27 UTC](https://forum.asana.com/t/moving-tasks-between-projects/84937/3 "2022-04-27T14:27:28Z")

</div>

Closed on 27 April 2022 14:27 UTC