Hi all,

I wonder what could be the best way to restore the timeline in case I or any team member has messed it up when dragging and dropping the tasks and dependencies. Is it possible to rollback to any earlier version of the project plan?

Thanks,
BR

Kristjan

I don’t think so. Asana does not really have a “state management”. They offer to cancel task deletion for example, but that’s it… @Marie any suggestion?

Welcome to the Forum @Kristjan_Otsmann and thanks for the mention @Bastien_Siebman!

I can confirm we don’t have an option to roll back changes; the best way to prevent that is to clearly communicate with your Team; if tasks are moved around despite this, you can always rely on the task history to restore your dependencies. You might also want to look into users permissions to mitigate these risks: https://asana.com/guide/help/permissions

Hope this helps Kristjan, please let us know if you have any follow up questions!