Is there a way to assign more than one resource to a task?
Hi @Vicki_Harbor
No. Deliverables should never have more than one owner. You can add multiple collaborators.
If the task is large enough to have two people working on it, consider parsing that work out into other tasks or subtasks and assign accordingly.
1 Like
lpb
#3
@Vicki_Harbor,
A task has only one assignee in Asana due to DRI (google “directly responsible individual”) but there are workarounds.
See the top of this post:
Also see my post here on one of the methods in more detail:
Thanks,
Larry
This topic was automatically closed after 5 days. New replies are no longer allowed.