How do I see what tasks are available?

Hello, I have many tasks within my project template that are dependant on other tasks. Im trying to see where I filter to see only those tasks I can actually work on now (where they are not waiting on a dependant task) … please let me know how to do this. As it is Im looking at a long list of tasks I cant actually work on.

Thanks
Stephanie

In Advanced Search under more you will see this option. You might try combinations.

. My assumptions are this

Blocking: A task that is not completed that a dependent task requires completion
Blocked: A task that is dependent on another task that has yet to be completed
Not Blocked: A dependent task that the predecessor task is completed.

I think your search should be Not Blocked and task that are Blocked that have a past due date.