I’m working on a portfolio containing multiple projects, all generated from a common master template through a centralized intake process.
Requirement:
Whenever a designated Go-Live task’s due date changes within a project, the corresponding project’s Go Live custom date field at the portfolio level should update automatically.
Limitation Identified:
-
Asana’s native automation supports this project-to-portfolio field synchronization at the individual project level.
-
However, the Bundle automation editor does not expose the same project/portfolio-level actions available in individual project rules.
-
Script Actions also do not appear to be available within Bundles, limiting centralized deployment.
-
Workaround Successfully Tested:
I developed a reusable JavaScript automation using Asana Script Actions that:
-
Detects changes to a Go-Live task’s due date.
-
Verifies the task’s
Task Type = Go-Live. -
Dynamically identifies the corresponding project without hardcoded project IDs.
-
Updates the existing portfolio-level Go Live custom date field.
The script has been successfully tested with actual field updates.
Question:
Is there a supported way to deploy this Script Action through a master project template, so every newly created project automatically inherits the trigger and script?
Alternatively, can a single centralized automation monitor Go-Live tasks across all projects within a portfolio, without creating individual project-level rules?
I’m also interested in recommended approaches for rolling this out to existing projects.
Any guidance, known limitations, or best practices would be appreciated.
Thanks!
-