Hi, I am trying to roll out Asana to our project management team. One of the key things we would like Asana to help us is to manage the cost. So we have day rate for different people and also actual working hours per project/tasks, does Asana have a function of calculating these two elements and show me the total cost per project/tasks?
Thanks for your help and looking forward to your reply,
Thanks,
Yi
1 Like
Hi @Yi_Wei,
It does not, unfortunately. However, @Bastien_Siebman has a service which can do this; I’m sure he’ll chime in here with more info.
1 Like
Thanks for your reply, do you have any recommendations on maybe integrated APP that can help for this purpose?
1 Like
I am doing a custom code for a client to do just that. We store roles daily costs as project custom fields, and a script updates the values every day. Let me know if you want to know more bastien@ido-clarity.com
PS: Asana does not have this natively
2 Likes
Hello, has this been added as a function yet to be able to add formulas into columns?