Seeking ideas of a suggested work around.
Context: Many projects I create for my team have due dates planned far in advance; often for a year out. Staff have expressed feeling overwhelmed and/or confused by seeing so many assignments and want their view to focus on what is imminent.
Ask: Within a project, I’d like to create a tab (list or board) that filters for tasks that are:
- Overdue
- Start Date has passed
- Due Date is within 60 days
Limitation I encountered using Filters: The maximum is “Due next 14 days” when I need “Due next 60 days” or even “Due next 30 days.” This product request is covered in the 2020 post: Expanded filter by due date
Limitation I encountered using Automations: I tried moving all long-term tasks to a collapsed “Pipeline” section and using an automation to bump them to an “Upcoming” section when the due date is within 60 days. However, this is not effective. The due date approaches without bumping the tasks appearing in the prioritized section.
Let me know if you see a way to improve my automation or have found another fix for this issue!