Hi Pradhuman,
Thanks for sharing this use case! I can understand how having to update rules manually every time a new sprint project is created can become repetitive. There are a couple of approaches you can consider, depending on your Asana subscription plan.
Solution 1: Project Templates (Asana Advanced plan)
If you’re on the Advanced plan, you can use a project template to standardize your sprint setup and automatically add newly created projects to your master portfolio.
Here’s how to configure it:
-
Create a project template: Configure all the required sections, custom fields, rules, and other sprint-related settings in the template.
-
Configure the template settings: Open the template’s Settings and, under Add projects to portfolios, select your master Sprint Portfolio. This ensures that projects created from the template are automatically added to the portfolio, provided the project creator has the necessary portfolio permissions.
-
Make the template easily accessible: Open your master portfolio, go to Customize → Project templates, and add your sprint template.
-
Create future sprints: From the portfolio, click Add work → Create project from template and select your sprint template.
I’ve attached screenshots showing these steps.
This way, every new sprint project created from the template starts with the required sections, custom fields, and rules, and is automatically added to the master portfolio. You don’t need to rebuild the configuration for every sprint.
Important limitation: Changes made to the template generally apply to projects created from it in the future. Existing sprint projects won’t automatically receive all subsequent template changes, so you’ll need to update those projects separately.
Solution 2: Bundles (Asana Enterprise and Enterprise+ plans)
If you’re on Enterprise or Enterprise+, you can explore Bundles for a more scalable approach, especially if you need to maintain the same workflow across both existing and newly created sprint projects.
Here’s how:
-
Create a project template containing your standard sprint structure.
-
Open the template’s customization options and create a new bundle.
-
Add the required sections and custom fields to the bundle, then configure the relevant rules.
-
Save the bundle and apply it to your master Sprint Portfolio.
-
Continue creating new sprint projects from your template, with the bundle providing the standardized workflow configuration.
The key advantage of bundles is that you can manage shared workflow components centrally. When you update a bundle, you can propagate supported changes across the existing projects using it, as well as use the updated configuration for new projects. This significantly reduces the effort required to maintain each sprint project individually.
Bundles also help govern shared workflow components, reducing the risk of individual projects drifting away from the standardized setup.
You can learn more in the official Asana Bundles documentation. Asana Help Center
My recommendation
If you’re on Advanced, start with Project Templates. They address the recurring setup work and ensure each new sprint project is added to the portfolio automatically.
If you’re on Enterprise or Enterprise+, consider Bundles when you also need to propagate workflow configuration changes across existing sprint projects without updating each one individually.
I hope this helps you streamline your sprint rollover process and reduce manual administration!