Duplicating plan - Lost Task Dates

Hello

I created a duplicate plan in Asana so we could model the impact of some change requests.

Unfortunately the start and end dates of the tasks in the original plan were lost when I created the duplicate and all stated the same date (20 October, when I created the duplicate).

Is there any way around this please?

Many thanks

Martin

Welcome, @Martin_Gee,

By “plan” do you mean an Asana Project?

Did you create it by Project actions menu > Duplicate? If so, then did you actively toggle on “Task due date” because it’s off by default:

Thanks,

Larry

Hi, yes I meant Project, and thank you for the tip, will look out for this in future.

Best wishes

Martin

1 Like

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.