Due Date Asana Rule

Hello.
Does anyone know how the Due Date Rule is working in Asana?
I customised the rule with next settings:
Trigger:
Due Date set - No due date
Action:
Set Due Date - 2

After I create a task but leave the field with the Due Date blanket nothing happens. Asana doesn’t run this trigger. Probably I do something wrong, if so, please advise what is wrong.

Hi @Vladimir_Lisichnik, welcome to the Asana Community Forum :wave:t2:

Great question! This rule will only run if a task previously had a due date and it was removed :slight_smile:

If you would like to automatically set a due date for tasks added to the project, you can use the trigger " + Task added to this project" instead.

I hope this helps! :slight_smile:

TY

1 Like

This topic was automatically closed after 6 days. New replies are no longer allowed.