# Dependent tasks - show still waiting or ready to start

**URL:** <https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930>\
**Category:** Ask the Community\
**Created:** [12 October 2020 00:57 UTC](https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930 "2020-10-12T00:57:25Z")\
**Posts on this page:** 4\
**Page:** 1

<div class="post-metadata">

**Author:** ![Holly\_Koogler](https://luna1.co/8d76cd.png) [@Holly\_Koogler](https://forum.asana.com/u/Holly_Koogler)\
**Post date:** [12 October 2020 00:57 UTC](https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930/1 "2020-10-12T00:57:25Z")

</div>

I’m brand new to Asana and trying to see if it could work for my team. We work on complex projects with a lot of dependencies. I’ve created an example project and added dependencies between the tasks. However I can’t tell when looking at My Tasks or any of the project views which tasks are ready to be done and which are dependent on something not yet completed. From googling I see this might be possible with Rules for Business users, but Premium is all we can afford. Is there a way to do this as a Premium user?

---

<div class="post-metadata">

**Author:** ![Emily\_Roman](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/emily_roman/32/283076_2.png) [@Emily\_Roman](https://forum.asana.com/u/Emily_Roman)\
**Post date:** [12 October 2020 07:32 UTC](https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930/2 "2020-10-12T07:32:37Z")

</div>

Hi @Holly_Koogler, welcome to the Asana Community Forum!

When you mark a task as [dependent on another](https://asana.com/guide/help/tasks/dependencies). You’ll see a yellow banner at the top of your task to let you know that it’s not ready to start yet.

Once your task is ready to start, you’ll receive a notification in your [Inbox](https://asana.com/guide/help/fundamentals/inbox) that you’re ready to get started. If the due date gets changed on the first task, you’ll receive a notification so you can update the due date for your dependent task accordingly.

 ![Screenshot 2020-10-12 at 08.29.00](https://us1.discourse-cdn.com/asana/original/3X/0/1/0128671313a5e91abdebd5bd9d25413d7cf0bda1.jpeg)

As it stands, it’s currently not possible to see if a task is dependent on another or if the task is ready to be done from your My Tasks list. You can click on the tasks to see more details and confirm if their status.

I hope this helps! 🙂

---

<div class="post-metadata">

**Author:** ![ShunS](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/shuns/32/115053_2.png) [@ShunS](https://forum.asana.com/u/ShunS)\
**Post date:** [24 January 2021 11:23 UTC](https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930/3 "2021-01-24T11:23:33Z")

</div>

Hi @Holly_Koogler,  
This might have become recently, but I can see that you can see the blocked/ready status in My Tasks too 🙂

 ![Screen Shot 2021-01-24 at 20.19.03](https://us1.discourse-cdn.com/asana/original/3X/a/f/af02b3c0ad80f4876bb340ee3363e4b2d9edf8a9.png)

In the screenshot, tasks C and D are waiting for other tasks, but tasks A and B can be started.

---

<div class="post-metadata">

**Author:** ![system](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/system/32/276370_2.png) [@system](https://forum.asana.com/u/system)\
**Post date:** [27 April 2022 14:15 UTC](https://forum.asana.com/t/dependent-tasks-show-still-waiting-or-ready-to-start/96930/4 "2022-04-27T14:15:33Z")

</div>

Closed on 27 April 2022 14:15 UTC