Custom fields are not linking between projects

It seems that whenever I add a task to another project, only the due date, assignee and tags are linking. Any other custom field I add is not linking between projects. Really need all of the fields of the task linking between projects. Help!

This should work correctly, as long as you:

  • Create the field in question as a Global field (not a project-specific field)
  • Apply that same global field to each project

I do this all the time and it works fine for me.

1 Like

Ok great, was having trouble figuring out how to make the field Global, but figured the field is made Global by adding it to the owner’s library. Thanks!

FYI I moved this thread from the Developers & API forum section to the Tips & Tricks section.