Copying existing tasks and subtasks into existing project template

Hello, does anyone know how to copy newly created tasks and subtasks into an existing project template I have (also) created? Thank you.

Hello @Mariska_van_Delft

Welcome to the Asana Forum :slight_smile:

The only way I am aware of is creating a new project out of the existing template > adding the tasks to the newly created project > saving the project as a template again > deleting the other, now obsolete, project template.

With this method, you’ll have the new tasks, but you will lose various template-specific settings like relative due dates and some others. So depending on how many tasks you are looking to add to the existing template, it might be worth just editing the existing template and adding the tasks manually in it.

Cheers,
Rosario

Thank you!