I copied recurring tasks to a new project and now when the user marks as complete they duplicate but for the same day. When the user marks as complete a second time, they then duplicate correctly for the next due date.
It is not every task or every user, I can’t see a pattern. Users are simply ticking as they usually would. Some users tick 10 tasks and 7 will be correct and 3 not.
What’s going on? Has anyone else had this?


#2

Sounds like a bug :thinking: you should move it to the bug category.