Can Asana track a task progress? For example:
a task started on Monday and it is ending on Friday. The amount of hours given is 20. Asana will split these 20 hours 4 per day (4 Monday, 4 Thursday,…). But today, which is Wednesday, i know that i’ve already worked on this task for 10 (or 6) hours instead of 8. Can Asana give me the amount of time remaining automatically? so 10 hours (or 14) in this case. If not, is it likely to see this as a new features?
Hi @Mirco_Leonessi you could always use custom fields as a work around with estimated time vs actual time. But currently it will not calculate the difference for you.