can a task in one project automatically change launch date when its dependency deaadline extends?

Can a task in one project automatically change launch date when its dependency deadline has to extend?

For example:
A social post will go live in ‘Campaigns’ project on monday.
Its dependency is a completed ‘pdf case study’ due on sunday, which is listed in our ‘Content’ project. This deadline has moved to Monday, so therefore we need to change the social media post in campaigns by a day.

Can the go-live date on the social post in Campaigns automatically update?

Hi @omega_goodwin, welcome to the Asana Community Forum! You can achieve this with our auto-shifting feature in Timeline view. You can find more details in this article: Creating task dependencies | Product guide • Asana.

I hope this helps! Let me know if you have any other questions :slight_smile:

1 Like