Is there a way to mark all open tasks in a project as complete the moment the project is archived?
Hi @Micha_Kuechler
No, this possibility is not offered at the moment.
By selecting several tasks, it is possible to validate them by pack of 50.
Julien
Hey @Julien_RENAUD
Thank you for your quick reply. So will rely more on good old human to human communication and ask my co-workers to complete all tasks before archiving a project. (and I’ve added a reminder task to do this in the project template)
Micha
1 Like
Just be careful with one thing: I consider it bad practice to complete a task you haven’t actually done. Instead cancel (mark as approval > reject) or make it obvious in the task name it wasn’t done…
Great. I like that.
This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.